Plantation/Enterprise Road

Forte and Tablada, Inc. was responsible for the Stage 0, Preliminary Scope, Budget Checklist and Stage 3 for this project. Additionally, Forte and Tablada, Inc. was responsible for preparing a construction proposal and construction engineering and inspection.  Urban Systems completed the traffic counts as a subconsultant. The purpose and need for the project was due to the roadway failing. The project would allow for a new wider, thicker base and overlay on the northern half and mill, patch and overlay for the southern half. Both would support higher traffic volumes. The project length totaled 1.781 miles. This project was successful in receiving funding and is nearing the completion of its construction phase.